FIELD NOTE 18 / DELIVERY
Same Machines, Half the Output
My first serious engineering project was at Iscor, South Africa’s state-owned steel maker, as a young industrial engineer fresh out of university. The project was the roll change on one of the rolling mills, where giant ingots were rolled down, shift after shift, into long coils of finished steel.
The rolls were enormous. They wore out and had to be changed often, and each change took at least one eight-hour shift. That was the number we had all inherited. A whole shift of lost production, planned for and accepted as the cost of running a steel mill.
I was new enough not to know yet what was supposed to be impossible. I spent days on the floor of the mill talking to the operators who did the changes. Not formal interviews, just watching and asking and listening. What I found is what every young engineer eventually finds if they bother to look. The operators knew exactly where the friction was. Each of them had a small catalogue of things that slowed the job down, and a small, quiet idea about how it could go faster. Nobody had asked.
I put a design together from what they told me, and a senior engineer refined it, improved it considerably in fact. When we implemented the new process, the eight-hour change came down to about forty-five minutes.
It was an OEE improvement so large that at first nobody quite believed the numbers. The equipment hadn’t changed. What changed was the organisation around it: the sequence of the steps, where the tools sat, how the parts were prepared, and the removal of dozens of small frictions the operators had lived with for years because nobody had asked them where the friction was.
Most businesses I have seen since Iscor are running at somewhere between forty and sixty per cent of the capacity they already own. The gap isn’t an investment problem. It is a friction problem, and the friction is nearly always invisible to the owner, because the owner isn’t the one standing at the machine or the desk when it shows up.
Structure drives behaviour. When friction is tolerated, not because anyone approves of it but because nobody has taken a disciplined look, the team adapts. They build workarounds, accept slower sequences and build the friction into their idea of what a reasonable day looks like. Over the years the friction becomes the operating standard, and the operating standard becomes the ceiling.
This is the work of PurgeAndPolish™, at the Delivery level of the GrowthForge™ pyramid. It is the 5S discipline applied to whatever the work actually is: sort, set in order, shine, standardise, sustain. In a steel mill that means where the tools live and the order of the steps. In a professional services firm it is the same discipline applied to information, files, templates and handovers. The principle doesn’t change with the industry. Take out the friction between the people and the work, and the same people with the same tools produce noticeably more in the same hours.
PurgeAndPolish™ isn’t cleaning, although things do end up cleaner. The real work is the disciplined removal of the dozens of small frictions every mature operation has quietly collected, and then putting in the structure that stops them collecting again.
Small issues compound, and on a production line they compound quickly. A two-minute friction repeated twenty times a shift is forty minutes. Across a team of five that is more than three hours a day, and across a year it is weeks of output the business pays for and doesn’t get. Each instance is too small to notice, which is exactly why nobody does.
You teach what you tolerate. A team living with invisible friction, because nobody has asked where it lives, is teaching itself that the current pace is the real pace. It almost never is.
There is a second lesson from Iscor that I have carried into every engagement since. The people on the floor nearly always know where the friction is. They built the workarounds and they live with the consequences. The engineer’s job, and the owner’s, isn’t to invent the answer from scratch. It is to ask the right people the right questions, capture what they already know, and give it back to them as a designed process.
Here is the question behind the question. When did you last stand on the floor of your own business and ask the people who do the work where the friction lives?
Not in a meeting, or a survey, or through a layer of supervisors. On the floor, in the actual work. What small daily frictions has your team adapted to and stopped mentioning? What would they change if you asked them directly and really listened? How much capacity is being soaked up every day by friction nobody would have designed in if they had been asked to design it in advance?
The answers usually sit just below the level of the reports most owners read. But the friction is the capacity. Removing it gives you capacity you already own and aren’t yet getting.
What good looks like is a business running near the top of its own installed capacity, because the friction between the people and the work has been deliberately taken out and deliberately kept out. The tools are where they belong. The sequence is what it is because someone designed it. And the operator’s quiet idea has been captured, credited and built in.
That is the move from firefighting to foresight in the productive part of the business. It doesn’t come from buying more equipment. It comes from taking seriously what the people using the current equipment already know.
At Iscor, eight hours became about forty-five minutes because a young engineer happened to ask. Most businesses I walk into have their own version of that eight-hour shift, waiting for someone to ask about it.
Friction is very hard to see from the owner’s desk, because the desk is usually two levels away from where it sits. The GrowthForge™ Diagnostic is twenty-five questions and takes about ten minutes. It gives your business a tier placement, from Fragile to Scalable, and shows where the biggest gap between installed capacity and actual output is likely to be. At Fragile or Emerging, this work usually follows stabilisation. At Developing or above, it tends to release the most capacity for the least investment.
Take the GrowthForge™ Diagnostic →
← Previous: Field Note 17 · The Bottleneck That Hides in Plain Sight · Next: Field Note 19 · When Reliability Is the Product →
Charles Barnard is a Growth Engineer with GrowthForge™. He works one-to-one with owner-led manufacturers and B2B distributors. Driven by Numbers. Powered by People. Engineered for Growth.